2015 | Insulation AB st. Stoupající a Klíčovská

The house, which was built in 1990 and was originally built by self-help of cooperatives, underwent thermal insulation, replacement of windows and repair of balconies. The construction was divided into two phases - autumn 2014 and spring 2015. Each of these stages had its own leadership. The work was realized by Trigema Building a.s. The total value of the order was CZK 10 million excluding VAT. Duration of implementation: 10/2014 - 06/2015

Revitalization of an apartment building in Prague 9, which included the cladding of the external cladding with a contact thermal insulation system, replacement of part of the opening fillings, glazing of loggias, balconies and balconies, laying of tiles on balconies and loggias.

Kontaktní formulář

Odesláním formuláře přijímám podmínky zpracování osobních údajů společností Trigema - jejich zpracování proběhne za účelem zaslání odpovědi na zadaný podnět a případné vytvoření obchodní nabídky.